Phase 4 – The Roof!

trusses

December 22 – After waiting for 2 weeks, the roof trusses for the house finally arrived this morning.  We have had two weeks of warm weather (the snow is pretty much all gone) but haven’t been able to do much without the trusses. Christmas comes early!

tall-wall

The tall wall also went up today – we had been waiting for the engineered wood for the uprights. Looks good.

2014_12_22tallwall

This is the view through the living room wall (where the window will be in early January).  There will be a second clerestory window above to provide light in the winter and views of the sky.