Phase 3 – The Walls

walls1

Nov 7 – Lower level exterior walls framed

walls2

Nov 11 – Lower level exterior walls sheathed.

walls5

Nov 28 – 2nd floor and walls above basement framed.

walls3

Nov 29 – Main floor framing continues (slab poured Nov 21 but then had 10″ of heavy wet snow and then cold weather for a few days).

2014-12-3topfloor

Dec 1 – Still cold. Framers almost finished main floor but we had to wait for some engineered wood for the tall wall.  Finally arrived on December 9.  Top floor floor and walls completed.